Construction Updates

Progress

Asphalt paving, concrete curb, gutter, and sidewalk work—along with sections of the asphalt bike path—are now complete between Redwood Road and 1400 West. Construction has now moved east, focusing on the north side of the road between 1400 West and 1000 West.

Current Work and Impacts

1400 West - 1200 West

Storm drain installation has wrapped up in this section. Curb, gutter, sidewalk, driveway, and asphalt replacement has begun and will take place through October.

You can expect during this work:

  • One travel lane in each direction.

  • Pedestrian/sidewalk access on the north side only. The south sidewalk is closed.

  • Intermittent driveway access closures are anticipated during times when crews are actively removing or replacing concrete. Properties anticipated to be impacted by driveway closures will be notified 48 hours in advance of any closure.

  • Backman Elementary School crossings are available at 1400 West and the Jordan River Bridge.

1200 West Intersection Closure

Northside of intersection is closed through the end of October for utility connection work. You can expect during this work:

  • Access to 1200 West from 1000 North.

  • East and westbound travel through the intersection will be maintained at all times, with one travel lane available in each direction.

  • No access to 600 North from 1200 West.

1200 West - 1000 West

Concrete driveway, sidewalk, and curb, & gutter installation takes place through October. Impacted properties will be notified in advance of restrictions to access. During this work, sidewalks on the north side will be closed. Pedestrians will be detoured to the south sidewalk. Asphalt paving in this section is anticipated to take place in late October. The work in this section is anticipated to be completed in late November.

You can expect:

  • One travel lane in each direction will be available.

  • Pedestrian/sidewalk access on the north side only. The south sidewalk is closed.

  • Intermittent driveway access closures are anticipated during times when crews are actively removing or replacing concrete. Properties anticipated to be impacted by driveway closures will be notified 48 hours in advance of any closure.

Please contact the project team for more information: